A production-grade stud wall calculator built for UK studwork: enter your wall length, height, stud centres, corners and openings to get an exact stud count, cut length and head/sole plate timber, plus a live wall diagram that redraws itself from your own numbers.
Studs to buy
21 studs
Live wall diagram
Drawn from your wall length, centres, wall ends and openings — not a stock image.
Stud count breakdown
Where the total stud count comes from.
Building a stud wall comes down to four numbers: how many field studs the stud centres call for, how many extra studs each corner needs, how many extra studs each door or window opening needs, and a waste allowance for cutting mistakes and damaged timber.
Convert wall length to millimetres, divide by your stud centres (600mm suits standard 12.5mm plasterboard; 400mm is used for thicker boards or extra stiffness), then add 1 for the stud that starts the run.
Each corner needs a 3-stud post so both intersecting stud walls have plasterboard backing, 2 studs more than the field stud already counted at that end.
Every door or window opening needs 2 full-height king studs and 2 shorter jack (trimmer) studs that carry the head timber's load down to the sole plate, 4 studs per opening. Short noggins (the UK term for the horizontal blocking pieces) above the head are typically cut from stud offcuts.
Add 5-10% on top of the raw total to cover bowed or split timber, cutting errors, and last-minute layout changes, then round up to a whole stud.
A 6 m wall, 2.4 m tall, framed at 600mm centres with corners at both ends and one door opening: field studs = floor(6000 ÷ 600) + 1 = 11. Corners add 2 × 2 = 4. The opening adds 4 more. That's 19 studs before waste; with a 10% allowance, ceil(19 × 1.10) = 21 studs. Each stud is cut to 2400mm − 135mm = 2265mm. The three plate runs need 6 m × 3 = 18 linear metres of timber, or six 3.6 m lengths after a small seam allowance.
Every timber stud wall is built from a handful of member types, each doing a different job. The diagrams below highlight one member at a time against the rest of the same opening, drawn in scale to real studwork, not stock photography.
The full-height stud repeated at every centre mark — 400mm or 600mm apart — that makes up most of a wall.
Full-height studs on both sides of an opening, running plate to plate, that the head timber (header) hangs from.
Shorter studs fixed to the inside of each king stud, cut to the opening height, that carry the head timber's load to the sole plate.
Short filler pieces above a head timber (and below a window cill), on the same layout as the field studs but cut shorter.
Three studs grouped where two stud walls meet (plan view above), giving plasterboard backing on both faces.
Where an internal partition meets a continuous wall, extra studs form a "T" so both sides of the junction have plasterboard backing too.
Field studs from wall length ÷ centres + 1, plus 2 per corner and 4 per opening, then round up 5-10% for waste.
600mm suits standard 12.5mm plasterboard; 400mm is used for thicker boards, tighter deflection, or extra load.
A standard 3-stud corner adds 2 studs beyond the field stud already counted.
4: two full-height king studs plus two jack (trimmer) studs. Noggins above the head are usually cut from offcuts.
45mm sole plate and a doubled 90mm head plate, standard for load-bearing studwork.